Qualifications

   

     

     

     

 ‚Äč

Related Projects

Our client needed a new air permit for its large cement storage and transfer terminal.  The challenge was new barge unloading and distribution equipment, including dust collectors sized for barge unloading of dry cement at a rate of up to 600 tons per hour.  GEC successfully worked with DEP during permit review to allow some construction activities to proceed in order to keep the project on track.  Our team coordinated regulatory site inspections, wrote the performance test protocol, and coordinated standard operating and maintenance procedures for our client.